Search for a warehouse execution system specification guide and you will find templates. Forty-page Word documents with checkbox feature matrices, a section titled “system requirements,” and a blank line where you fill in your company name.

I have been the person who signs off on those packages. Somewhere north of 300 spec-and-test document sets over seven years — call it 280, I would have to pull the log — and I have sent back more than half of the first drafts. Not because the specs were wrong. Because they were written for a different project than the one being built.

Most buyers spend their time on the feature matrix. Does the WES do wave release, does it do dynamic slotting, does it talk to this PLC or that one. What they skip are the two things that actually decide whether the project works: how throughput gets measured, and who owns the interface after handover. Those two items are also where the cheapest bid tends to go quiet.

So before you open a template, work out which situation you are in. It is not about company size. It is about one question: who is still responsible for this system eighteen months after go-live?

Three answers, three different documents.

  • Greenfield, with in-house engineering. You are buying performance outcomes, and you can verify them yourself.
  • Brownfield, and the WMS stays. You are buying an interface boundary, not a feature list.
  • One automation island. You are buying an acceptance test. The spec is secondary.

Scenario A: Greenfield, and you have engineers who can hold the supplier accountable

In this situation the spec should describe what the system has to achieve and how you will prove it, not how the supplier should build it. The moment you write the architecture into the document, you have taken on design risk and left the supplier holding only execution risk. You will still pay for their engineers.

The single most useful thing you can put in a greenfield WES specification is a throughput definition. Not a number. A definition, with the calculation method attached.

Two suppliers quoting “1,200 tote moves per hour” have told you nothing until you know which cycle mix produced that figure. FEM 9.851, the European Materials Handling Federation standard for storage and retrieval machine performance data, defines throughput through cycle times — single cycle, combined cycle, with defined pick and drop points — rather than through one headline number. Require every bidder to submit the cycle assumptions behind their figure using the same method.

That one clause does more for bid comparability than a hundred rows of feature checkboxes. It also shortens evaluation by a week or two, because suppliers who cannot reproduce the math stop pretending.

For the software side, the WES specification should ask for three artifacts that almost never appear in a downloaded template:

  1. A data dictionary — not an API list, a dictionary. Field names, types, units, allowed values, and who owns each field.
  2. A version policy. How upgrades work, how much notice you get, what breaks.
  3. A named integration owner on the supplier side, with decision authority spelled out.

Item three is the one that gets negotiated away and the one you will miss most. “Our integration team will handle it” is not a name.

Safety references belong here too, and they should be citable clause numbers, not adjectives. If the design includes automated guided vehicles, ANSI/ITSDF B56.5 and EN ISO 3691-4 both cover driverless industrial trucks and their systems. If it includes storage and retrieval machines, ANSI/ASME B30.13 governs that equipment family. UL 3100 covers automated mobile platforms and is comparatively new, so check the edition before you cite it.

On benchmarking: it is fine to name the systems your committee has seen. Dematic’s AS/RS and AGV lines come up in a lot of these discussions because they are widely deployed, and there is nothing wrong with using them as a reference point. What you cannot do is write “equivalent to Dematic” into a requirement. That sentence converts a measurable spec into an argument about intent.

Scenario B: Brownfield, and the WMS is staying

Most of the bad specifications I have reviewed came out of this situation. Not because the people writing them were careless, but because they started in the wrong place.

Start with the do-not-change list

The instinct is to write down everything the new WES will do. The more useful first document is a list of what will not be touched, and why. Which WMS transactions stay exactly as they are. Which conveyor zones keep their existing control logic. Which reports people will still pull from the old system because that is how the shift meeting runs.

You want that list because the brownfield failure mode is not a missing feature. It is a well-intentioned improvement that quietly breaks a downstream process nobody documented. I watched a routing change that looked obviously correct take out a labeling step that had been hand-built in 2016 and had no spec at all.

Why “wcs sourcing” gives people the wrong idea

Searching for wcs sourcing usually means you expect a product comparison, the way you would compare barcode scanners. WCS is not a product on a shelf. It is a configuration layer built against your conveyor zones, your sorter induct logic, your AGV traffic rules, and your WMS transaction model. Two WCS “prices” are not comparable until the interface boundary is fixed, because until then you are comparing two different scopes that happen to share a label.

The practical consequence: in a brownfield project, the WCS section of your spec should read like a responsibility matrix, not a feature list. Who changes code when the WMS schema moves. Who runs the integration test. Who answers the phone at 2am when a tote disappears between the sorter and the AS/RS. Who pays the change order when the honest answer is “both of you.”

Write those four answers into the contract. They are boring. They are also the difference between a project that closes and a project that becomes a standing meeting.

Put fault injection in the acceptance test

Brownfield systems fail at the seams, so test the seams. Drop a PLC heartbeat during peak simulation. Kill the WMS interface mid-wave. Pull power from one aisle and watch what the WES tells the operators. If your acceptance test only proves the happy path, it proves the part of the system that was never in doubt.

Scenario C: One automation island, and nobody in IT has spare cycles

Here is the advice that normally gets pushback: in a single-subsystem deployment, do not write an eighty-page specification. Write fifteen to twenty pages, and put the weight on the acceptance test, the performance metric, and the exit terms.

Why. The marginal value of a specification drops fast when there is nobody on your side to enforce it. A detailed functional spec assumes you have engineers who will read the supplier’s design documents and catch the drift. If you do not, the spec becomes a document the supplier writes to and you file. The acceptance test, by contrast, is something you can actually run.

  • Performance: a measurable rate at a defined load, with the measurement method named.
  • Acceptance: a scripted test with pass/fail criteria, run on your floor, with your SKUs.
  • Spares: a list with part numbers and lead times, for the five items most likely to fail first.
  • Handover: training hours, documentation set, and who signs off that it happened.
  • Exit: what happens to the software licence and the configuration data if you change vendors.

That last one matters more than people expect. Configuration data — the map, the traffic rules, the zone logic — is often the least portable asset in the entire deployment, and nobody thinks about it until year four.

Keep the safety references in even at this size. Whether you are deploying a Dematic AGV fleet or three units from a regional integrator, the clause numbers are the same and they do not care about project budget. ANSI/ITSDF B56.5, and EN ISO 3691-4 where it applies, are the ones that come up for driverless vehicles sharing floor space with people.

What you can skip: the thousand-row feature matrix. On a single-island project it mostly generates negotiation instead of information.

Which one are you actually in?

Three questions. The answers usually line up.

1. Will your team maintain the WES configuration after go-live, or will the supplier? If your team, you are in A or B, and the spec needs the data dictionary and the version policy. If the supplier holds a support contract and your team never touches the configuration, you are closer to C, and contract terms matter more than design detail.

2. Is the existing WMS going to be there in five years? If yes, you are in B, and the interface boundary is essentially the whole document. If the WMS is being replaced inside the same program, treat it as A — but budget for a much longer integration test than anyone proposes.

3. Is this one subsystem, or the first of several? This is the question people get wrong most often. A single AGV fleet today is frequently aisle two of a larger rollout in eighteen months. If there is any realistic chance of that, write the C document but bolt on the interface definitions from B. Retrofitting them later costs more than writing them now.

And the price question, since it always comes up. The savings from taking the lower bid on a WES or WCS package tend to show up as a line item in month one. The cost of an ambiguous interface shows up in month nine, as change orders. On one program I remember the gap between the two shortlisted bids was around $180,000 — no, closer to $140,000, and most of it was licensing. The change orders that came out of the unresolved interface boundary passed that number inside two quarters. I do not have the final figure in front of me and I am not going to make one up.

That is the whole argument for writing the boring sections properly. Not because documentation is virtuous, but because the alternative is paying for the same scope twice.

One last thing, and it is a genuine limitation. All of this reflects what I was reviewing as of Q1 2025. Standards get revised — ANSI/ITSDF B56.5 was updated in 2019, EN ISO 3691-4 was published in 2020, and UL 3100 is still relatively new — so confirm the current edition before you put a clause number in a contract. The scenarios hold up better than the citations do.

Jane Smith
Jane Smith

I’m Jane Smith, a senior content writer with over 15 years of experience in the packaging and printing industry. I specialize in writing about the latest trends, technologies, and best practices in packaging design, sustainability, and printing techniques. My goal is to help businesses understand complex printing processes and design solutions that enhance both product packaging and brand visibility.